For the investor Pro-Ing doo from Novi Sad, we performed works on the production and assembly of steel structures
of the evaporator facility in the “Biospringer RS” yeast production plant in Senta. The building consists of a hall for
accommodation of equipment and a platform for carrying tanks and installations. The platform at a height of +3.7m contains
concrete slab, at that level beams with brains for connecting concrete and steel beams were made.
Due to the aggressive environment, the complete structure is galvanized. Screws were used to connect the structure
class 12.9.
- INVESTORPro Ing doo
- LOCATIONSenta
- OBJECT TYPEConstruction for evaporator and tube bridge
- DIMENSIONS21x19m
- WEIGHT OF CONSTRUCTION53t
- THE DURATION OF THE PROJECT12.11.2019 - 30.03.2020
- CATEGORY Production complexes