Railway bridge in Niš

The existing steel structure of the bridge at km 4+871.5 on railway line 219 Crveni Krst (Niš) – Zaječar –
Prahovo Pristanište, bridges the main road Nikola Tesla Boulevard. The construction is
damaged in February 2022.
The new bridge structure is designed very similarly to the existing one. The axle is retained
spacing of the main supports of 3600 mm- This spacing is dictated by the places that are intended for accommodation
bearings on pillars. The new orthotropic plate consists of longitudinal supports – open ribs made of
sheets. The transverse supports are at a distance of 2280 mm. The new bridge, like the existing one, has pedestrian crossings on both sides
tracks for official use.

  • INVESTORBricken doo
  • LOCATIONNiš
  • OBJECT TYPETransport infrastructure
  • PROJECT DIMENSIONS17267mm
  • WEIGHT OF CONSTRUCTION37t
  • THE DURATION OF THE PROJECT10.2022.-11.2022.